Canadian Natural Resources says it has approved another expansion of its Horizon oilsands mine but must revisit the scope of the project because of unexpectedly robust production from two previous expansions.
Horizon, which was designed with a maximum capacity of 182,000 barrels per day, is churning out 205,000 bpd of upgraded bitumen, the Calgary-based oil and natural gas producer said Thursday.
Engineering work is taking place to determine how much more the plant can handle, CEO Steve Laut said on a conference call with analysts.
Get breaking National news
“Just to be clear though, this is a good problem to have,” said Laut.
The expansion, expected to take place this summer during a maintenance shutdown, is intended to ease the bottleneck. The company has said the project could cost about $70 million and add between 5,000 and 15,000 bpd of capacity.
READ MORE: Canadian Natural Resources to spend less on Horizon oilsands project in 2017, more on exploration
- Vancouver working to avoid ‘the great sigh’ following FIFA World Cup excitement
- Port of Vancouver expansion project referred to Canada’s Major Projects Office
- Close to 800,000 have applied for $100 rebate, payments coming: Alberta’s Smith
- Canfor closing Prince George pulp mill, hundreds of jobs lost
Output from that expansion is anticipated to begin in the fall, the same time as new production would come from a separate $1-billion, 80,000-bpd expansion at Horizon.
Earlier Thursday, Canadian Natural said it had total oil and natural gas liquids production of almost 600,000 bpd in the first quarter ended March 31, slightly better than the 547,000 bpd in the same period a year ago.
Net income was $245 million, an improvement from a net loss of $105 million a year ago.
Revenue after royalty payments was $3.64 billion, up from $2.18 billion in the first quarter of 2016, as average realized oil prices more than doubled.